Y25t back into operation 25.06.2011

We put the Y25t back into operation on the 22nd of June, and yesterday we had the first operation of the machine while connected to a SCADA system. This allowed us to monitor and record all systems, and everything checked ok. The production was in line with the expectation, given a significant wave which was estimated to be 1m high and with 4.5s period, in a very irregular sea state.